2-Unit Kg Block with Ancillary Facilities
Project Detail

2-Unit Kg Block with Ancillary Facilities

2-Unit Kg Block with Ancillary Facilities

StatusOngoing
Last Updated StatusRoofing level
Progress50%
CategoryEducation
LocationWudzrolo
ContractorPavic Construction Company Limited
Implementing BodyCentral Tongu District Assembly
Start Date13 Nov 2025
Expected Completion13 May 2026
Last Updated28 Mar 2026
Progress Tracker